Return to Start Page



This is going to be one of these work letters.  We are in the process of implementing many different environmental projects to comply with the latest EPA regulations.  This is one of those projects.  We are installing the ability to inject activated carbon into the duct work of the units.  The activated carbon adsorbs the mercury with in the flue gas and then the activated carbon is collected in the scrubber towers.  This addition or carbon should allow the units to be compliant with the new Mercury and Air Toxins Rule (or MATS).  It goes into affect for Apache Station in April of 2016.



The activated carbon injection system requires a silo (the highlight of this letter) to house the carbon which comes in as a powder and is then pneumatically conveyed to injection lances located in the ducts.  This project happens to be one of mine.  The silo came in on a truck and was set down on the road horizontally.  We employed the use of some cranes to stand it up.



The cranes used were supplied from Marco Crane and Rigging Company.  We had a 95 ton tail crane with a 275 ton head crane.  The idea was to lift the silo up with the head crane and use the tail crane to rotate it to vertical prior to disconnecting.  Once the tail crane let go, then the head crane would simply swing the silo into place.



The silo (although it is not obvious) has a slopped bottom of 60 degrees.  All of the injection equipment is located withing the bottom of the silo structure (or skirt).  The silo has the ability to hold a 10 day supply of carbon when we are operating both units at full load around the clock. 

As we are planning to switch the fuel on one of the units from coal to gas, that will increase the silo to a 20 day supply as it is only required on the coal burning unit.



The lift was fairly smooth.  The only glitch was in the transition from the horizontal to vertical position, the two slack slings got caught on a flange on the silo roof.  We had to lower the silo top and use a man lift to hold the cables out of the way while the transition was made.


On a side note, one of the crane operators is a guy that I graduated with from high school.  His name is Ben Beamis.  I hadn't seen him since high school, but his parents still live in San Manual.



This activated carbon equipment will allow the mercury emissions to be reduced from the current rate of 4~6 pounds of mercury per Trillion Btus (TBtu) burned in the furnace to reduced to 1.2 pounds of mercury emitted per TBtu.  The heat rate of the unit is roughly 10,300 Btu per kWh.  The units are 195 MW (295,000 kW).  So if my calculations are correct, at full load each unit burns 1.76 x 10^13 Btu per year.  So reducing the mercury by 4.6 pounds per trillion Btu will reduce the mercury emitted by 0.3 pounds per year.

If you get bored, run the math and let me know if I did that correct.



After the silo was erected we flew up the catwalk to access the top of the silo.  During the design phase, we opted to not have a ladder access to the top of the silo, but rather use a catwalk from the unit.  This cost a little extra, but I didn't want to have to climb up 80 feet to reach the top.

So far it seems to be coming together pretty well.



Below is a photo I took on the way into the plant on Monday.  With it being winter time, the sand hill cranes are back for the winter and they were flying across the road as I was driving in.  Pretty sight, but they are sure loud.







Return to Start Page